a piece of work can be finished in 8 days, what part of the work is done in 2 days​

Respuesta :

kaseyafa
kaseyafa kaseyafa
  • 03-02-2022

Answer:

1/4 of the work

Step-by-step explanation:

A quarter (1/4) of the work is done in 2 days. Let's break it down:

Work can be finished in 8 days total so with 2 days it is only partially completed. If we set it up as 2/8 we can simplify to get 1/4. Therefore, we know only a quarter of the work is done so far.

Answer Link

Otras preguntas

Provide a clear answer while explaining how to do each step to the question below: Which of the following expressions are equivalent to [tex]\sqrt[3]{8x^5y^7}[/
Simplify the given expression. Assume that no variable equals 0. (14x20y10 / 28x12y14)4
Which one is better EBAY or AMAZON + why? BRAINLIEST WILL BE GIVEN
why is it so important to record all the data in a science experiment​
In need of some help. Thank you very much and advance it’s greatly appreciated
what effect did the eastern front have on world war I
How many ways can a president, vice-president, secretary, and treasurer be chosen from a club with 8 members?
In the figure, AB || CD. Find x and y. A) x=33, y=131 B) x= 53, y= 131 C) x= 37, y= 147 D) x= 131, y= 53
what is HPLC? List its basic parts and state their functions​
I DON’T GET THIS ONLY NEED NUMBER 6 PLEASEEE!!!!!