15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

X-intercept (__,__) Y-intercept (__,__)
what is a fractional banking system
How many plants grew per square foot
PLZ PLZ ✨✨✨✨ HELP WILL GIVE BRAINLIEST
Which does NOT describe how much the man can eat or drink? this soliloquy?
Multiply (3.2 x 103) x (1.5 x 103)
Factor completely: x2 + 10x + 24 (Which is the right answer?) Prime (x + 12)(x + 2) (x + 3)(x + 8) (x + 6)(x + 4)
Jon ran around a track that was 1\8 of a mile long.He ran around the track 24 times.How many miles did Jon run?
Hhat are five natural resources economics question
Coach Cardio's class is doing pushups. Kai has her back and legs in a straight line and hands under her shoulders. Jason is keeping a slight bend in his knees