it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

What was the main aim of operation torch which was launched by the allies
which statement explains why John Adams most likely supported the separation of powers between the branches of the new national government? Question 1 options:
PLEASE HELP, HISTORY!!!! What was Herbert Hoover and the Food Administration do in WWI?
a cricket ball of 70g moving with a velocity of 0.5 m/s is stopped by a player in 0.5s what is the force applied to stop the ball
Complete the sentence. The lower the hydrogen ion concentration, the ______ the pH. higher lower closer to 7 closer to 0
What was a result of the industrial revolution in the United States
what materials were commonly used to make each type of art during this period
An organization is implementing a preselected baseline of security controls, but finds not all of the controls apply. What should they do?A. Implement all of th
What is the value of x?
Organisms are classified, or grouped into categories, based on similarities in their characteristics and/or evolutionary relationships. The study of how organi